7 CFR § 1710.207 - RUS criteria for load forecasts by distribution borrowers.

---
identifier: "/us/cfr/t7/s1710.207"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "7 CFR § 1710.207 - RUS criteria for load forecasts by distribution borrowers."
title_number: 7
title_name: "Agriculture"
section_number: "1710.207"
section_name: "RUS criteria for load forecasts by distribution borrowers."
chapter_name: "RURAL UTILITIES SERVICE, DEPARTMENT OF AGRICULTURE"
part_number: "1710"
part_name: "GENERAL AND PRE-LOAN POLICIES AND PROCEDURES COMMON TO ELECTRIC LOANS AND GUARANTEES"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "7 U.S.C. 901  1921  and 6941"
regulatory_source: "57 FR 1053, Jan. 9, 1992, unless otherwise noted."
cfr_part: "1710"
---

# 1710.207 RUS criteria for load forecasts by distribution borrowers.

Load forecasts submitted by distribution borrowers that are unaffiliated with a power supply borrower, or by distribution borrowers that are members of a power supply borrower that has a total utility plant less than $500 million and that is not itself a member of another power supply borrower with a total utility plant of $500 million or more must satisfy the following minimum criteria:

(a) The borrower considered all known relevant factors that influence the consumption of electricity and the known number of consumers served at the time the study was developed;

(b) The borrower considered and identified all loads on its system of RE Act beneficiaries and non-RE Act beneficiaries;

(c) The borrower developed an adequate supporting data base and considered a range of relevant assumptions; and

(d) The borrower provided RUS with adequate documentation and assistance to allow for a thorough and independent review.

[65 FR 14786, Mar. 20, 2000, as amended at 84 FR 32611, July 9, 2019]