Skip to content
LexBuild

10 CFR § 52.33 - Duration of renewal.

---
identifier: "/us/cfr/t10/s52.33"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "10 CFR § 52.33 - Duration of renewal."
title_number: 10
title_name: "Energy"
section_number: "52.33"
section_name: "Duration of renewal."
chapter_name: "NUCLEAR REGULATORY COMMISSION"
part_number: "52"
part_name: "LICENSES, CERTIFICATIONS, AND APPROVALS FOR NUCLEAR POWER PLANTS"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "Atomic Energy Act of 1954, secs. 103, 104, 147, 149, 161, 181, 182, 183, 185, 186, 189, 223, 234 (42 U.S.C. 2133, 2134, 2167, 2169, 2201, 2231, 2232, 2233, 2235, 2236, 2239, 2273, 2282); Energy Reorganization Act of 1974, secs. 201, 202, 206, 211 (42 U.S.C. 5841, 5842, 5846, 5851); 44 U.S.C. 3504 note."
regulatory_source: "72 FR 49517, Aug. 28, 2007, unless otherwise noted."
cfr_part: "52"
---

# 52.33 Duration of renewal.

Each renewal of an early site permit may be for not less than 10, nor more than 20 years, plus any remaining years on the early site permit then in effect before renewal.