10 CFR § 95.23 - Termination of facility clearance.
---identifier: "/us/cfr/t10/s95.23"source: "ecfr"legal_status: "authoritative_unofficial"title: "10 CFR § 95.23 - Termination of facility clearance."title_number: 10title_name: "Energy"section_number: "95.23"section_name: "Termination of facility clearance."chapter_name: "NUCLEAR REGULATORY COMMISSION"part_number: "95"part_name: "FACILITY SECURITY CLEARANCE AND SAFEGUARDING OF NATIONAL SECURITY INFORMATION AND RESTRICTED DATA"positive_law: falsecurrency: "2026-03-24"last_updated: "2026-03-24"format_version: "1.1.0"generator: "[email protected]"authority: "Atomic Energy Act of 1954, secs. 145, 161, 223, 234 (42 U.S.C. 2165, 2201, 2273, 2282); Energy Reorganization Act of 1974, sec. 201 (42 U.S.C. 5841); 44 U.S.C. 3504 note; E.O. 10865, as amended, 25 FR 1583, 3 CFR, 1959-1963 Comp., p. 398; E.O. 12829, 58 FR 3479, 3 CFR, 1993 Comp., p. 570; E.O. 12968, 60 FR 40245, 3 CFR, 1995 Comp., p. 391; E.O. 13526, 75 FR 707, 3 CFR, 2009 Comp., p. 298."regulatory_source: "45 FR 14483, Mar. 5, 1980, unless otherwise noted."cfr_part: "95"---
Identifier
/us/cfr/t10/s95.23
Currency
2026-03-24
Positive Law
No
Updated
2026-03-24
Chapter
Nuclear Regulatory Commission
Authority
Atomic Energy Act of 1954, secs. 145, 161, 223, 234 (42 U.S.C. 2165, 2201, 2273, 2282); Energy Reorganization Act of 1974, sec. 201 (42 U.S.C. 5841); 44 U.S.C. 3504 note; E.O. 10865, as amended, 25 FR... Atomic Energy Act of 1954, secs. 145, 161, 223, 234 (42 U.S.C. 2165, 2201, 2273, 2282); Energy Reorganization Act of 1974, sec. 201 (42 U.S.C. 5841); 44 U.S.C. 3504 note; E.O. 10865, as amended, 25 FR 1583, 3 CFR, 1959-1963 Comp., p. 398; E.O. 12829, 58 FR 3479, 3 CFR, 1993 Comp., p. 570; E.O. 12968, 60 FR 40245, 3 CFR, 1995 Comp., p. 391; E.O. 13526, 75 FR 707, 3 CFR, 2009 Comp., p. 298.
# 95.23 Termination of facility clearance.(a) Facility clearance will be terminated when—(1) There is no longer a need to use, process, store, reproduce, transmit, transport or handle classified matter at the facility; or(2) The Commission makes a determination that continued facility clearance is not in the interest of national security.(b) When facility clearance is terminated, the licensee, certificate holder, or other person will be notified in writing of the determination and the procedures outlined in § 95.53 apply.[62 FR 17692, Apr. 11, 1997, as amended at 72 FR 49562, Aug. 28, 2007]