Skip to content
LexBuild

10 CFR § 501.103 - OFE decision.

---
identifier: "/us/cfr/t10/s501.103"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "10 CFR § 501.103 - OFE decision."
title_number: 10
title_name: "Energy"
section_number: "501.103"
section_name: "OFE decision."
chapter_name: "DEPARTMENT OF ENERGY"
subchapter_number: "E"
subchapter_name: "ALTERNATE FUELS"
part_number: "501"
part_name: "ADMINISTRATIVE PROCEDURES AND SANCTIONS"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "42 U.S.C. 7101  42 U.S.C. 8301  42 U.S.C. 8701  E.O. 12009, 42 FR 46267; 28 U.S.C. 2461 note."
regulatory_source: "46 FR 59889, Dec. 7, 1981, unless otherwise noted."
cfr_part: "501"
---

# 501.103 OFE decision.

(a) OFE shall issue an appropriate rule or order after considering the request for modification or rescission of a rule or order and other relevant information received during the proceeding.

(b) OFE will either grant or deny the request for modification or rescission and will briefly state the pertinent facts and legal basis for the decision.

(c) OFE will serve the rule or order granting or denying the request for modification or rescission upon the requester, or, if the action was initiated by OFE, upon the owner or operator of the affected powerplant or installation. OFE will publish a notice of the issuance of a rule or order modifying or rescinding a rule or order in the *Federal Register.*