Skip to content
LexBuild

10 CFR § 503.7 - State approval—general requirement for new powerplants.

---
identifier: "/us/cfr/t10/s503.7"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "10 CFR § 503.7 - State approval—general requirement for new powerplants."
title_number: 10
title_name: "Energy"
section_number: "503.7"
section_name: "State approval—general requirement for new powerplants."
chapter_name: "DEPARTMENT OF ENERGY"
subchapter_number: "E"
subchapter_name: "ALTERNATE FUELS"
part_number: "503"
part_name: "NEW FACILITIES"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "Department of Energy Organization Act, Pub. L. 95-91, 91 Stat. 565 (42 U.S.C. § 7101 ); Powerplant and Industrial Fuel Use Act of 1978, Pub. L. 95-620, 92 Stat. 3289 (42 U.S.C. 8301 ); Energy Security Act, Pub. L. 96-294, 94 Stat. 611 (42 U.S.C. 8701 ); E.O. 1209, 42 FR 46267, September 15, 1977."
regulatory_source: "46 FR 59903, Dec. 7, 1981, unless otherwise noted."
cfr_part: "503"
---

# 503.7 State approval—general requirement for new powerplants.

(a) Where approvals by the appropriate State regulatory authority are required prior to the construction or use of a new powerplant, a petition for an exemption for consideration by OFE may be submitted to OFE prior to obtaining such approvals from the State regulatory authority.

(b) An exemption granted for a powerplant shall not become effective until an adequate demonstration has been made to OFE that all applicable approvals required by the State regulatory authorities have been obtained.