Skip to content
LexBuild

18 CFR § 4.108 - Contents of application for exemption from provisions other than licensing.

---
identifier: "/us/cfr/t18/s4.108"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "18 CFR § 4.108 - Contents of application for exemption from provisions other than licensing."
title_number: 18
title_name: "Conservation of Power and Water Resources"
section_number: "4.108"
section_name: "Contents of application for exemption from provisions other than licensing."
chapter_name: "FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY"
subchapter_number: "B"
subchapter_name: "REGULATIONS UNDER THE FEDERAL POWER ACT"
part_number: "4"
part_name: "LICENSES, PERMITS, EXEMPTIONS, AND DETERMINATION OF PROJECT COSTS"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "16 U.S.C. 791a-825r; 42 U.S.C. 7101-7352."
regulatory_source: "Order 141, 12 FR 8485, Dec. 19, 1947, unless otherwise noted."
cfr_part: "4"
---

# 4.108 Contents of application for exemption from provisions other than licensing.

An application for exemption of a small hydroelectric power project from provisions of Part I of the Act other than the licensing requirement need not be prepared according to any specific format, but must be included as an identified appendix to the related application for license or amendment of license. The application for exemption must list all sections or subsections of Part I of the Act for which exemption is requested.

[Order 106, 45 FR 76123, Nov. 18, 1980]