Skip to content
LexBuild

20 CFR § 725.476 - Issuance of decision and order.

---
identifier: "/us/cfr/t20/s725.476"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "20 CFR § 725.476 - Issuance of decision and order."
title_number: 20
title_name: "Employees' Benefits"
section_number: "725.476"
section_name: "Issuance of decision and order."
chapter_name: "OFFICE OF WORKERS' COMPENSATION PROGRAMS, DEPARTMENT OF LABOR"
subchapter_number: "B"
subchapter_name: "FEDERAL COAL MINE HEALTH AND SAFETY ACT OF 1969, AS AMENDED"
part_number: "725"
part_name: "CLAIMS FOR BENEFITS UNDER PART C OF TITLE IV OF THE FEDERAL MINE SAFETY AND HEALTH ACT, AS AMENDED"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "5 U.S.C. 301; 28 U.S.C. 2461 note (Federal Civil Penalties Inflation Adjustment Act of 1990); Pub. L. 114-74 at sec. 701; Reorganization Plan No. 6 of 1950, 15 FR 3174; 30 U.S.C. 901  902(f), 921, 932, 936; 33 U.S.C. 901  42 U.S.C. 405; Secretary's Order 10-2009, 74 FR 58834."
regulatory_source: "65 FR 80054, Dec. 20, 2000, unless otherwise noted."
cfr_part: "725"
---

# 725.476 Issuance of decision and order.

Within 20 days after the official termination of the hearing (see § 725.475), the administrative law judge shall issue a decision and order with respect to the claim making an award to the claimant, rejecting the claim, or taking such other action as is appropriate.