23 CFR § 630.705 - Procedures.

---
identifier: "/us/cfr/t23/s630.705"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "23 CFR § 630.705 - Procedures."
title_number: 23
title_name: "Highways"
section_number: "630.705"
section_name: "Procedures."
chapter_name: "FEDERAL HIGHWAY ADMINISTRATION, DEPARTMENT OF TRANSPORTATION"
subchapter_number: "G"
subchapter_name: "ENGINEERING AND TRAFFIC OPERATIONS"
part_number: "630"
part_name: "PRECONSTRUCTION PROCEDURES"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "23 U.S.C. 106, 109, 112, 115, 315, and 402(a); sec. 1110, 1501, and 1503, Pub. L. 109-59, 119 Stat. 1144; Pub. L. 105-178, 112 Stat. 193; Pub. L. 104-59, 109 Stat. 582; Pub. L. 97-424, 96 Stat. 2106; Pub. L. 90-495, 82 Stat. 828; Pub. L. 85-767, 72 Stat. 896; Pub. L. 84-627, 70 Stat. 380; sections 1303 and 1405, Pub. L. 112-141, 126 Stat. 405; and 23 CFR 1.32 and 49 CFR 1.81 and 1.85."
cfr_part: "630"
---

# 630.705 Procedures.

(a) An advance construction project shall meet the same requirements and be processed in the same manner as a regular Federal-aid project, except,

(1) The FHWA authorization does not constitute any commitment of Federal funds on the project, and

(2) The FHWA shall not reimburse the State until the project is converted under § 630.709.

(b) [Reserved]

[60 FR 36993, July 19, 1995, as amended at 68 FR 60033, Oct. 21, 2003; 90 FR 40737, Aug. 21, 2025]