Skip to content
LexBuild

23 CFR § 636.201 - What selection procedures and award criteria may be used?

---
identifier: "/us/cfr/t23/s636.201"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "23 CFR § 636.201 - What selection procedures and award criteria may be used?"
title_number: 23
title_name: "Highways"
section_number: "636.201"
section_name: "What selection procedures and award criteria may be used?"
chapter_name: "FEDERAL HIGHWAY ADMINISTRATION, DEPARTMENT OF TRANSPORTATION"
subchapter_number: "G"
subchapter_name: "ENGINEERING AND TRAFFIC OPERATIONS"
part_number: "636"
part_name: "DESIGN-BUILD CONTRACTING"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "Sec. 1503 of Pub. L. 109-59, 119 Stat. 1144; Sec. 1307 of Pub. L. 105-178, 112 Stat. 107; 23 U.S.C. 101, 109, 112, 113, 114, 115, 119, 128, and 315; 49 CFR 1.48(b)."
regulatory_source: "67 FR 75926, Dec. 10, 2002, unless otherwise noted."
cfr_part: "636"
---

# 636.201 What selection procedures and award criteria may be used?

You should consider using two-phase selection procedures for all design-build projects. However, if you do not believe two-phase selection procedures are appropriate for your project (based on the criteria in § 636.202), you may use a single phase selection procedure or the modified-design-build contracting method. The following procedures are available:

| Selection procedure | Criteria for using a selection procedure | Award criteria options |
| --- | --- | --- |
| (a) Two-Phase Selection Procedures (RFQ followed by RFP) | § 636.202 | Lowest price, Adjusted low-bid (price per quality point), meets criteria/low bid, weighted criteria process, fixed price/best design, best value. |
| (b) Single Phase (RFP) | Project not meeting the criteria in § 636.202 | All of the award criteria in item (a) of this table. |
| (c) Modified Design-Build (may be one or two phases) | Any project | Lowest price technically acceptable. |