Skip to content
LexBuild

30 CFR § 57.6407 - Circuit testing.

---
identifier: "/us/cfr/t30/s57.6407"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "30 CFR § 57.6407 - Circuit testing."
title_number: 30
title_name: "Mineral Resources"
section_number: "57.6407"
section_name: "Circuit testing."
chapter_name: "MINE SAFETY AND HEALTH ADMINISTRATION, DEPARTMENT OF LABOR"
subchapter_number: "K"
subchapter_name: "METAL AND NONMETAL MINE SAFETY AND HEALTH"
part_number: "57"
part_name: "SAFETY AND HEALTH STANDARDS—UNDERGROUND METAL AND NONMETAL MINES"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "30 U.S.C. 811."
regulatory_source: "50 FR 4082, Jan. 29, 1985, unless otherwise noted."
cfr_part: "57"
---

# 57.6407 Circuit testing.

A blasting galvanometer or other instrument designed for testing blasting circuits shall be used to test the following:

(a) In surface operations—

(1) Continuity of each electric detonator in the blasthole prior to stemming and connection to the blasting line;

(2) Resistance of individual series or the resistance of multiple balanced series to be connected in parallel prior to their connection to the blasting line;

(3) Continuity of blasting lines prior to the connection of electric or electronic detonator series; and

(4) Total blasting circuit resistance prior to connection to the power source.

(b) In underground operations—

(1) Continuity of each electric detonator series; and

(2) Continuity of blasting lines prior to the connection of electric or electronic detonators.