30 CFR § 285.631 - When must I initiate activities under an approved COP?

---
identifier: "/us/cfr/t30/s285.631"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "30 CFR § 285.631 - When must I initiate activities under an approved COP?"
title_number: 30
title_name: "Mineral Resources"
section_number: "285.631"
section_name: "When must I initiate activities under an approved COP?"
chapter_name: "BUREAU OF SAFETY AND ENVIRONMENTAL ENFORCEMENT, DEPARTMENT OF THE INTERIOR"
subchapter_number: "B"
subchapter_name: "OFFSHORE"
part_number: "285"
part_name: "RENEWABLE ENERGY AND ALTERNATE USES OF EXISTING FACILITIES ON THE OUTER CONTINENTAL SHELF"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "43 U.S.C. 1331"
regulatory_source: "88 FR 6413, Jan. 31, 2023, unless otherwise noted."
cfr_part: "285"
---

# 285.631 When must I initiate activities under an approved COP?

After your COP is approved, you must commence construction by the date given in the construction schedule required by 30 CFR 585.626(b)(21), and included as a part of your approved COP, unless BOEM approves a deviation from your schedule.