Skip to content
LexBuild

30 CFR § 285.632 - What documents must I submit before I may construct and install facilities under my approved COP?

---
identifier: "/us/cfr/t30/s285.632"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "30 CFR § 285.632 - What documents must I submit before I may construct and install facilities under my approved COP?"
title_number: 30
title_name: "Mineral Resources"
section_number: "285.632"
section_name: "What documents must I submit before I may construct and install facilities under my approved COP?"
chapter_name: "BUREAU OF SAFETY AND ENVIRONMENTAL ENFORCEMENT, DEPARTMENT OF THE INTERIOR"
subchapter_number: "B"
subchapter_name: "OFFSHORE"
part_number: "285"
part_name: "RENEWABLE ENERGY AND ALTERNATE USES OF EXISTING FACILITIES ON THE OUTER CONTINENTAL SHELF"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "43 U.S.C. 1331"
regulatory_source: "88 FR 6413, Jan. 31, 2023, unless otherwise noted."
cfr_part: "285"
---

# 285.632 What documents must I submit before I may construct and install facilities under my approved COP?

(a) You must submit to BSEE the documents listed in the following table:

| Document: | Requirements are found in: |
| --- | --- |
| (1) Facility Design Report | § 285.701 |
| (2) Fabrication and Installation Report | § 285.702 |

(b) You must submit your safety management system, as required by § 285.810.

(c) These activities must fall within the scope of your approved COP. If they do not fall within the scope of your approved COP, you will be required to submit a revision to your COP, under 30 CFR 585.634, for BOEM approval before commencing the activity.