Skip to content
LexBuild

30 CFR § 285.910 - What must I do when I remove my facility?

---
identifier: "/us/cfr/t30/s285.910"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "30 CFR § 285.910 - What must I do when I remove my facility?"
title_number: 30
title_name: "Mineral Resources"
section_number: "285.910"
section_name: "What must I do when I remove my facility?"
chapter_name: "BUREAU OF SAFETY AND ENVIRONMENTAL ENFORCEMENT, DEPARTMENT OF THE INTERIOR"
subchapter_number: "B"
subchapter_name: "OFFSHORE"
part_number: "285"
part_name: "RENEWABLE ENERGY AND ALTERNATE USES OF EXISTING FACILITIES ON THE OUTER CONTINENTAL SHELF"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "43 U.S.C. 1331"
regulatory_source: "88 FR 6413, Jan. 31, 2023, unless otherwise noted."
cfr_part: "285"
---

# 285.910 What must I do when I remove my facility?

(a) You must remove all facilities to a depth of 15 feet below the mudline, unless otherwise authorized by BSEE.

(b) Within 60 days after you remove a facility, you must verify to BSEE that you have cleared the site.