Skip to content
LexBuild

30 CFR § 585.632 - What documents must I submit before I may construct and install facilities under my approved COP?

---
identifier: "/us/cfr/t30/s585.632"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "30 CFR § 585.632 - What documents must I submit before I may construct and install facilities under my approved COP?"
title_number: 30
title_name: "Mineral Resources"
section_number: "585.632"
section_name: "What documents must I submit before I may construct and install facilities under my approved COP?"
chapter_name: "BUREAU OF OCEAN ENERGY MANAGEMENT, DEPARTMENT OF THE INTERIOR"
subchapter_number: "B"
subchapter_name: "OFFSHORE"
part_number: "585"
part_name: "RENEWABLE ENERGY ON THE OUTER CONTINENTAL SHELF"
positive_law: false
currency: "2026-04-05"
last_updated: "2026-04-05"
format_version: "1.1.0"
generator: "[email protected]"
authority: "43 U.S.C. 1337."
regulatory_source: "88 FR 6430, Jan. 31, 2023, unless otherwise noted."
cfr_part: "585"
---

# 585.632 What documents must I submit before I may construct and install facilities under my approved COP?

(a) You must submit to BSEE the documents listed in the following table:

| Document: | Requirements are found in: |
| --- | --- |
| (1) Facility Design Report | 30 CFR 285.701. |
| (2) Fabrication and Installation Report | 30 CFR 285.702. |

(b) You must submit your Safety Management System, as required by 30 CFR 285.810.

(c) These activities must fall within the scope of your approved COP. If they do not fall within the scope of your approved COP, you will be required to submit a revision to your COP, under § 585.634, for BOEM approval before commencing the activity.