Skip to content
LexBuild

40 CFR § 60.1615 - How do I comply with the increment of progress for awarding contracts?

---
identifier: "/us/cfr/t40/s60.1615"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "40 CFR § 60.1615 - How do I comply with the increment of progress for awarding contracts?"
title_number: 40
title_name: "Protection of Environment"
section_number: "60.1615"
section_name: "How do I comply with the increment of progress for awarding contracts?"
chapter_name: "ENVIRONMENTAL PROTECTION AGENCY"
subchapter_number: "C"
subchapter_name: "AIR PROGRAMS"
part_number: "60"
part_name: "STANDARDS OF PERFORMANCE FOR NEW STATIONARY SOURCES"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "42 U.S.C. 7401"
regulatory_source: "36 FR 24877, Dec. 23, 1971, unless otherwise noted."
cfr_part: "60"
---

# 60.1615 How do I comply with the increment of progress for awarding contracts?

You must submit a signed copy of the contracts awarded to initiate onsite construction, initiate onsite installation of emission control equipment, and incorporate process changes. Submit the copy of the contracts with the notification that the increment of progress has been achieved. You do not need to include documents incorporated by reference or the attachments to the contracts.