Skip to content
LexBuild

40 CFR § 60.2140 - By what date must I conduct the initial performance test?

---
identifier: "/us/cfr/t40/s60.2140"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "40 CFR § 60.2140 - By what date must I conduct the initial performance test?"
title_number: 40
title_name: "Protection of Environment"
section_number: "60.2140"
section_name: "By what date must I conduct the initial performance test?"
chapter_name: "ENVIRONMENTAL PROTECTION AGENCY"
subchapter_number: "C"
subchapter_name: "AIR PROGRAMS"
part_number: "60"
part_name: "STANDARDS OF PERFORMANCE FOR NEW STATIONARY SOURCES"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "42 U.S.C. 7401"
regulatory_source: "36 FR 24877, Dec. 23, 1971, unless otherwise noted."
cfr_part: "60"
---

# 60.2140 By what date must I conduct the initial performance test?

(a) The initial performance test must be conducted within 60 days after your CISWI reaches the charge rate at which it will operate, but no later than 180 days after its initial startup.

(b) If you commence or recommence combusting a solid waste at an existing combustion unit at any commercial or industrial facility, and you conducted a test consistent with the provisions of this subpart while combusting the solid waste within the 6 months preceding the reintroduction of that solid waste in the combustion chamber, you do not need to retest until 6 months from the date you reintroduce that solid waste.

(c) If you commence or recommence combusting a solid waste at an existing combustion unit at any commercial or industrial facility and you have not conducted a performance test consistent with the provisions of this subpart while combusting the solid waste within the 6 months preceding the reintroduction of that solid waste in the combustion chamber, you must conduct a performance test within 60 days from the date you reintroduce that solid waste.