Skip to content
LexBuild

40 CFR § 60.2706 - By what date must I conduct the initial air pollution control device inspection?

---
identifier: "/us/cfr/t40/s60.2706"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "40 CFR § 60.2706 - By what date must I conduct the initial air pollution control device inspection?"
title_number: 40
title_name: "Protection of Environment"
section_number: "60.2706"
section_name: "By what date must I conduct the initial air pollution control device inspection?"
chapter_name: "ENVIRONMENTAL PROTECTION AGENCY"
subchapter_number: "C"
subchapter_name: "AIR PROGRAMS"
part_number: "60"
part_name: "STANDARDS OF PERFORMANCE FOR NEW STATIONARY SOURCES"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "42 U.S.C. 7401"
regulatory_source: "36 FR 24877, Dec. 23, 1971, unless otherwise noted."
cfr_part: "60"
---

# 60.2706 By what date must I conduct the initial air pollution control device inspection?

(a) The initial air pollution control device inspection must be conducted within 60 days after installation of the control device and the associated CISWI reaches the charge rate at which it will operate, but no later than 180 days after the final compliance date for meeting the amended emission limitations.

(b) Within 10 operating days following an air pollution control device inspection, all necessary repairs must be completed unless the owner or operator obtains written approval from the state agency establishing a date whereby all necessary repairs of the designated facility must be completed.