Skip to content
LexBuild

40 CFR § 62.14540 - When must I complete each increment of progress?

---
identifier: "/us/cfr/t40/s62.14540"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "40 CFR § 62.14540 - When must I complete each increment of progress?"
title_number: 40
title_name: "Protection of Environment"
section_number: "62.14540"
section_name: "When must I complete each increment of progress?"
chapter_name: "ENVIRONMENTAL PROTECTION AGENCY"
subchapter_number: "C"
subchapter_name: "AIR PROGRAMS"
part_number: "62"
part_name: "APPROVAL AND PROMULGATION OF STATE PLANS FOR DESIGNATED FACILITIES AND POLLUTANTS"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "42 U.S.C. 7401"
regulatory_source: "43 FR 51393, Nov. 3, 1978, unless otherwise noted."
cfr_part: "62"
---

# 62.14540 When must I complete each increment of progress?

If you plan to come into compliance after October 4, 2004, you must meet the two increments of progress specified in paragraphs (a) and (b) of this section.

(a) Increment 1. Submit a final control plan by April 5, 2004.

(b) Increment 2. Reach final compliance by October 3, 2005.