Skip to content
LexBuild

40 CFR § 62.15040 - What are the requirements for meeting increments of progress and achieving final compliance?

---
identifier: "/us/cfr/t40/s62.15040"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "40 CFR § 62.15040 - What are the requirements for meeting increments of progress and achieving final compliance?"
title_number: 40
title_name: "Protection of Environment"
section_number: "62.15040"
section_name: "What are the requirements for meeting increments of progress and achieving final compliance?"
chapter_name: "ENVIRONMENTAL PROTECTION AGENCY"
subchapter_number: "C"
subchapter_name: "AIR PROGRAMS"
part_number: "62"
part_name: "APPROVAL AND PROMULGATION OF STATE PLANS FOR DESIGNATED FACILITIES AND POLLUTANTS"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "42 U.S.C. 7401"
regulatory_source: "43 FR 51393, Nov. 3, 1978, unless otherwise noted."
cfr_part: "62"
---

# 62.15040 What are the requirements for meeting increments of progress and achieving final compliance?

(a) *Class I units.* If you plan to achieve compliance more than 1 year following the effective date of this subpart and a permit modification is not required, or more than 1 year following the date of issuance of a revised construction or operation permit if a permit modification is required, you must meet five increments of progress:

(1) Submit a final control plan.

(2) Submit a notification of retrofit contract award.

(3) Initiate onsite construction.

(4) Complete onsite construction.

(5) Achieve final compliance.

(b) *Class II units.* If you plan to achieve compliance more than 1 year following the effective date of this subpart and a permit modification is not required, or more than 1 year following the date of issuance of a revised construction or operation permit if a permit modification is required, you must meet two increments of progress:

(1) Submit a final control plan.

(2) Achieve final compliance.