40 CFR § 62.15080 - How do I comply with the increment of progress for completing onsite construction?

---
identifier: "/us/cfr/t40/s62.15080"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "40 CFR § 62.15080 - How do I comply with the increment of progress for completing onsite construction?"
title_number: 40
title_name: "Protection of Environment"
section_number: "62.15080"
section_name: "How do I comply with the increment of progress for completing onsite construction?"
chapter_name: "ENVIRONMENTAL PROTECTION AGENCY"
subchapter_number: "C"
subchapter_name: "AIR PROGRAMS"
part_number: "62"
part_name: "APPROVAL AND PROMULGATION OF STATE PLANS FOR DESIGNATED FACILITIES AND POLLUTANTS"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "42 U.S.C. 7401"
regulatory_source: "43 FR 51393, Nov. 3, 1978, unless otherwise noted."
cfr_part: "62"
---

# 62.15080 How do I comply with the increment of progress for completing onsite construction?

You must complete onsite construction and installation of emission control equipment and complete process changes outlined in the final control plan.