40 CFR § 73.18 - Submittal procedures for units commencing commercial operation during the period from January 1, 1993, through December 31, 1995.
---
identifier: "/us/cfr/t40/s73.18"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "40 CFR § 73.18 - Submittal procedures for units commencing commercial operation during the period from January 1, 1993, through December 31, 1995."
title_number: 40
title_name: "Protection of Environment"
section_number: "73.18"
section_name: "Submittal procedures for units commencing commercial operation during the period from January 1, 1993, through December 31, 1995."
chapter_name: "ENVIRONMENTAL PROTECTION AGENCY"
subchapter_number: "C"
subchapter_name: "AIR PROGRAMS"
part_number: "73"
part_name: "SULFUR DIOXIDE ALLOWANCE SYSTEM"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "42 U.S.C. 7601 and 7651"
cfr_part: "73"
---
# 73.18 Submittal procedures for units commencing commercial operation during the period from January 1, 1993, through December 31, 1995.
(a) *Eligibility.* To be eligible for allowances under this section, a unit shall commence commercial operation between January 1, 1993, and December 31, 1995, and have commenced construction before December 31, 1990.
(b) *Application for allowances.* No later than December 31, 1995, the designated representative for a unit expected to be eligible under this provision must submit a photocopy of a signed contract for the construction of the unit.
(c) *Commencement of commercial operation.* The Administrator will use EIA information submitted by the utility for the boiler on-line date as commencement of commercial operation.
[58 FR 15710, Mar. 23, 1993]