Skip to content
LexBuild

43 CFR § 404.19 - What requirements must be met before I can request assistance to conduct a feasibility study?

---
identifier: "/us/cfr/t43/s404.19"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "43 CFR § 404.19 - What requirements must be met before I can request assistance to conduct a feasibility study?"
title_number: 43
title_name: "Public Lands: Interior"
section_number: "404.19"
section_name: "What requirements must be met before I can request assistance to conduct a feasibility study?"
chapter_name: "BUREAU OF RECLAMATION, DEPARTMENT OF THE INTERIOR"
part_number: "404"
part_name: "RECLAMATION RURAL WATER SUPPLY PROGRAM"
positive_law: false
currency: "2026-04-05"
last_updated: "2026-04-05"
format_version: "1.1.0"
generator: "[email protected]"
authority: "Public Law 109-451 (43 U.S.C. 2401 )"
regulatory_source: "73 FR 67782, Nov. 17, 2008, unless otherwise noted."
cfr_part: "404"
---

# 404.19 What requirements must be met before I can request assistance to conduct a feasibility study?

All of the following requirements must be met before you can request assistance to conduct a feasibility study:

(a) An appraisal investigation must be completed, with or without assistance from Reclamation;

(b) Reclamation must have reviewed any appraisal investigation prepared without its assistance;

(c) Reclamation must have prepared an appraisal report evaluating the appraisal investigation; and,

(d) The appraisal report must include a recommendation by Reclamation, if appropriate, that a feasibility study should be conducted, as described in § 404.45.