43 CFR § 431.5 - Cost data and fund requirements.

---
identifier: "/us/cfr/t43/s431.5"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "43 CFR § 431.5 - Cost data and fund requirements."
title_number: 43
title_name: "Public Lands: Interior"
section_number: "431.5"
section_name: "Cost data and fund requirements."
chapter_name: "BUREAU OF RECLAMATION, DEPARTMENT OF THE INTERIOR"
part_number: "431"
part_name: "GENERAL REGULATIONS FOR POWER GENERATION, OPERATION, MAINTENANCE, AND REPLACEMENT AT THE BOULDER CANYON PROJECT, ARIZONA/NEVADA"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "Reclamation Act of 1902 (32 Stat. 388), Boulder Canyon Project Act of 1928 (43 U.S.C. 617 ), Boulder Canyon Project Adjustment Act of 1940 (43 U.S.C. 618 ), Colorado River Storage Project Act of 1956 (43 U.S.C. 620 ), Colorado River Basin Project Act of 1968 (43 U.S.C. 1501 ), and Hoover Power Plant Act of 1984 (98 Stat. 1333)."
regulatory_source: "51 FR 23962, July 1, 1986, unless otherwise noted."
cfr_part: "431"
---

# 431.5 Cost data and fund requirements.

Reclamation shall submit annually on or before April 15 to Western and Contractors, cost data, including one year of actual costs for the last completed fiscal year and estimated costs for the next 5 fiscal years, for operation, maintenance, replacements, additions and betterments, non-Federal funds advanced for the uprating program by non-Federal purchasers, and interest on and amortization of the Federal investment. Such cost data shall identify major items. Upon 5 days prior written notice to Reclamation, any Contractor shall have the right, subject to applicable Federal laws and regulations, to review records used to prepare such cost data at Reclamation offices during regular business hours. Contractors shall have an opportunity to present written views within 30 days of the transmittal of the cost data. Reclamation responses to written views shall be provided within 60 days of transmittal of the cost data or 30 days after a meeting with Contractors convened pursuant to § 431.4(d), whichever is later.