Skip to content
LexBuild

43 CFR § 3261.11 - How do I apply for approval of drilling operations and well pad construction?

---
identifier: "/us/cfr/t43/s3261.11"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "43 CFR § 3261.11 - How do I apply for approval of drilling operations and well pad construction?"
title_number: 43
title_name: "Public Lands: Interior"
section_number: "3261.11"
section_name: "How do I apply for approval of drilling operations and well pad construction?"
chapter_name: "BUREAU OF LAND MANAGEMENT, DEPARTMENT OF THE INTERIOR"
subchapter_number: "C"
subchapter_name: "MINERALS MANAGEMENT (3000)"
part_number: "3200"
part_name: "GEOTHERMAL RESOURCE LEASING"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "30 U.S.C. 1001-1028; 43 U.S.C. 1701  and Pub. L. 109-58."
regulatory_source: "72 FR 24400, May 2, 2007, unless otherwise noted."
cfr_part: "3200"
---

# 3261.11 How do I apply for approval of drilling operations and well pad construction?

(a) Send to BLM:

(1) A completed and signed drilling permit application, Form 3260-2;

(2) A complete operations plan (§ 3261.12);

(3) A complete drilling program (§ 3261.13); and

(4) An acceptable bond (§ 3261.18).

(b) Do not start any drilling operations until after BLM approves the permit.