Skip to content
LexBuild

43 CFR § 3276.13 - What additional information must I give BLM in the monthly report for flash and dry steam facilities?

---
identifier: "/us/cfr/t43/s3276.13"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "43 CFR § 3276.13 - What additional information must I give BLM in the monthly report for flash and dry steam facilities?"
title_number: 43
title_name: "Public Lands: Interior"
section_number: "3276.13"
section_name: "What additional information must I give BLM in the monthly report for flash and dry steam facilities?"
chapter_name: "BUREAU OF LAND MANAGEMENT, DEPARTMENT OF THE INTERIOR"
subchapter_number: "C"
subchapter_name: "MINERALS MANAGEMENT (3000)"
part_number: "3200"
part_name: "GEOTHERMAL RESOURCE LEASING"
positive_law: false
currency: "2026-04-05"
last_updated: "2026-04-05"
format_version: "1.1.0"
generator: "[email protected]"
authority: "30 U.S.C. 1001-1028; 43 U.S.C. 1701  and Pub. L. 109-58."
regulatory_source: "72 FR 24400, May 2, 2007, unless otherwise noted."
cfr_part: "3200"
---

# 3276.13 What additional information must I give BLM in the monthly report for flash and dry steam facilities?

In addition to the regular monthly report information required by § 3276.12, send to BLM:

(a) Steam flow into the turbine in klbs; for dual flash facilities, you must separate the steam flow into high pressure steam and low pressure steam;

(b) Condenser pressure in psia;

(c) Condenser temperature in deg. F;

(d) Auxiliary steam flow used for gas ejectors, steam seals, pumps, etc., in klbs;

(e) Flow of condensate out of the plant (after the cooling towers) in klbs; and

(f) Any other information we may require.