Skip to content
LexBuild

43 CFR § 3282.11 - May a participating area continue if there is intermittent unit production?

---
identifier: "/us/cfr/t43/s3282.11"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "43 CFR § 3282.11 - May a participating area continue if there is intermittent unit production?"
title_number: 43
title_name: "Public Lands: Interior"
section_number: "3282.11"
section_name: "May a participating area continue if there is intermittent unit production?"
chapter_name: "BUREAU OF LAND MANAGEMENT, DEPARTMENT OF THE INTERIOR"
subchapter_number: "C"
subchapter_name: "MINERALS MANAGEMENT (3000)"
part_number: "3280"
part_name: "GEOTHERMAL RESOURCES UNIT AGREEMENTS"
positive_law: false
currency: "2026-04-05"
last_updated: "2026-04-05"
format_version: "1.1.0"
generator: "[email protected]"
authority: "30 U.S.C. 1001-1028 and 43 U.S.C. 1701"
regulatory_source: "72 FR 24432, May 2, 2007, unless otherwise noted."
cfr_part: "3280"
---

# 3282.11 May a participating area continue if there is intermittent unit production?

A participating area may continue if there is intermittent unit production only if BLM determines that intermittent production is in the public interest. For example, a direct use facility may only require production to occur during winter months.