Skip to content
LexBuild

43 CFR § 3282.6 - When must the unit operator propose to revise a participating area boundary?

---
identifier: "/us/cfr/t43/s3282.6"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "43 CFR § 3282.6 - When must the unit operator propose to revise a participating area boundary?"
title_number: 43
title_name: "Public Lands: Interior"
section_number: "3282.6"
section_name: "When must the unit operator propose to revise a participating area boundary?"
chapter_name: "BUREAU OF LAND MANAGEMENT, DEPARTMENT OF THE INTERIOR"
subchapter_number: "C"
subchapter_name: "MINERALS MANAGEMENT (3000)"
part_number: "3280"
part_name: "GEOTHERMAL RESOURCES UNIT AGREEMENTS"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "30 U.S.C. 1001-1028 and 43 U.S.C. 1701"
regulatory_source: "72 FR 24432, May 2, 2007, unless otherwise noted."
cfr_part: "3280"
---

# 3282.6 When must the unit operator propose to revise a participating area boundary?

(a) The unit operator must submit a written application to BLM to revise a participating area boundary no later than 60 days after receipt of the BLM determination described herein, when either:

(1) A well is completed that BLM has determined will produce or utilize in commercial quantities, and such well:

(i) Is located outside of an existing participating area; or

(ii) Drains an area outside the existing participating area; or

(2) An injection well located outside of an existing participating area is put into use that BLM has determined provides reservoir pressure support to production.

(b) The unit operator may submit a written application for a revision of a participating area when new or additional technical information or revised interpretations of any information provides a basis for revising the boundary.

(c) The unit operator may submit a written request to BLM to delay a participation area revision decision when drilling multiple wells in the unit is actively pursued or the drilling is providing additional technical information. A delay will not affect the effective date of any participation area revision (see § 3282.7). The request must include:

(1) The well locations;

(2) Anticipated spud and completion dates of each well;

(3) The timing of well testing and analyses of technical information; and

(4) The anticipated date BLM will receive the participation area revision for review.

(d) BLM will provide the unit operator with a written decision on the application to revise a participating area or the request to delay a participating area revision decision by BLM.