Skip to content
LexBuild

44 CFR § 80.21 - Closeout requirements.

---
identifier: "/us/cfr/t44/s80.21"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "44 CFR § 80.21 - Closeout requirements."
title_number: 44
title_name: "Emergency Management and Assistance"
section_number: "80.21"
section_name: "Closeout requirements."
chapter_name: "FEDERAL EMERGENCY MANAGEMENT AGENCY, DEPARTMENT OF HOMELAND SECURITY"
subchapter_number: "B"
subchapter_name: "INSURANCE AND HAZARD MITIGATION"
part_number: "80"
part_name: "PROPERTY ACQUISITION AND RELOCATION FOR OPEN SPACE"
positive_law: false
currency: "2026-04-05"
last_updated: "2026-04-05"
format_version: "1.1.0"
generator: "[email protected]"
authority: "Robert T. Stafford disaster relief and emergency assistance act, 42 U.S.C. 5121 through 5207; the National Flood Insurance Act of 1968, as amended, 42 U.S.C. 4001  Homeland Security Act of 2002, 6 U.S.C. 101."
regulatory_source: "72 FR 61743, Oct. 31, 2007, unless otherwise noted."
cfr_part: "80"
---

# 80.21 Closeout requirements.

Upon closeout of the grant, the subrecipient, through the recipient, must provide FEMA, with the following:

(a) A copy of the deed recorded for each property, demonstrating that each property approved in the original application was mitigated and that the deed restrictions recorded are consistent with the FEMA model deed restriction language to meet the requirements of this part;

(b) A photo of each property site after project completion;

(c) The latitude-longitude coordinates of each property site;

(d) Identification of each property as a repetitive loss structure, if applicable; and

(e) Other information as determined by the Administrator.

[73 FR 61743, Oct. 31, 2007, as amended at 86 FR 50672, Sept. 10, 2021]