46 CFR § 56.97-25 - Preparation for testing (modifies 137.2).

---
identifier: "/us/cfr/t46/s56.97-25"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "46 CFR § 56.97-25 - Preparation for testing (modifies 137.2)."
title_number: 46
title_name: "Shipping"
section_number: "56.97-25"
section_name: "Preparation for testing (modifies 137.2)."
chapter_name: "COAST GUARD, DEPARTMENT OF HOMELAND SECURITY"
subchapter_number: "F"
subchapter_name: "MARINE ENGINEERING"
part_number: "56"
part_name: "PIPING SYSTEMS AND APPURTENANCES"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "33 U.S.C. 1321(j), 1509; 43 U.S.C. 1333; 46 U.S.C. 3306, 3703; E.O. 12234, 45 FR 58801, 3 CFR, 1980 Comp., p. 277; E.O. 12777, 56 FR 54757, 3 CFR, 1991 Comp., p. 351; DHS Delegation No. 00170.1, Revision No. 01.4."
regulatory_source: "CGFR 68-82, 33 FR 18843, Dec. 18, 1968, unless otherwise noted."
cfr_part: "56"
---

# 56.97-25 Preparation for testing (modifies 137.2).

(a) *Exposure of joints.* All joints including welds must be left uninsulated and exposed for examination during the test.

(b) *Addition of temporary supports.* Piping systems designed for vapor or gas may be provided with additional temporary supports, if necessary.

(c) *Restraint or isolation of expansion joints.* Expansion joints must be provided with temporary restraint, if required for the additional pressure load under test.

(d) *Isolation of equipment not subjected to pressure test.* Equipment that is not to be subjected to the pressure test must be isolated by a blank flange or equivalent means.

(e) *Treatment of flanged joints containing blinds.* Flanged joints at which blinds are inserted to blank off other equipment during the test need not be tested.

(f) *Precautions against test medium expansion.* If a pressure test is to be maintained for a period of time and the test medium in the system is subject to thermal expansion, precautions must be taken to avoid excessive pressure. A small relief valve set to 1 1/3 times the test pressure is recommended during the pressure test.

[CGD 73-254, 40 FR 40167, Sept. 2, 1975]