48 CFR § 16.207-3 - 16.207-3 Limitations.
---
identifier: "/us/cfr/t48/s16.207-3"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "48 CFR § 16.207-3 - 16.207-3 Limitations."
title_number: 48
title_name: "Federal Acquisition Regulations System"
section_number: "16.207-3"
section_name: "16.207-3 Limitations."
chapter_number: 1
chapter_name: "FEDERAL ACQUISITION REGULATION"
subchapter_number: "C"
subchapter_name: "CONTRACTING METHODS AND CONTRACT TYPES"
part_number: "16"
part_name: "TYPES OF CONTRACTS"
positive_law: false
currency: "2026-04-05"
last_updated: "2026-04-05"
format_version: "1.1.0"
generator: "[email protected]"
authority: "41 U.S.C. 1121(b); 40 U.S.C. 121(c); 10 U.S.C. chapter 4 and 10 U.S.C. chapter 137 legacy provisions (see 10 U.S.C. 3016); and 51 U.S.C. 20113."
regulatory_source: "48 FR 42219, Sept. 19, 1983, unless otherwise noted."
cfr_part: "16"
---
# 16.207-3 16.207-3 Limitations.
This contract type may be used only when—
(a) The work required cannot otherwise be clearly defined;
(b) The required level of effort is identified and agreed upon in advance;
(c) There is reasonable assurance that the intended result cannot be achieved by expending less than the stipulated effort; and
(d) The contract price is the simplified acquisition threshold or less, unless approved by the chief of the contracting office.
[48 FR 42219, Sept. 19, 1983, as amended at 75 FR 53133, Aug. 30, 2010; 85 FR 40067, July 2, 2020]