Skip to content
LexBuild

48 CFR § 33.213 - 33.213 Obligation to continue performance.

---
identifier: "/us/cfr/t48/s33.213"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "48 CFR § 33.213 - 33.213   Obligation to continue performance."
title_number: 48
title_name: "Federal Acquisition Regulations System"
section_number: "33.213"
section_name: "33.213   Obligation to continue performance."
chapter_number: 1
chapter_name: "FEDERAL ACQUISITION REGULATION"
subchapter_number: "E"
subchapter_name: "GENERAL CONTRACTING REQUIREMENTS"
part_number: "33"
part_name: "PROTESTS, DISPUTES, AND APPEALS"
positive_law: false
currency: "2026-04-05"
last_updated: "2026-04-05"
format_version: "1.1.0"
generator: "[email protected]"
authority: "41 U.S.C. 1121(b); 40 U.S.C. 121(c); 10 U.S.C. chapter 4 and 10 U.S.C. chapter 137 legacy provisions (see 10 U.S.C. 3016); and 51 U.S.C. 20113."
cfr_part: "33"
---

# 33.213 33.213   Obligation to continue performance.

(a) In general, before passage of the Disputes statute, the obligation to continue performance applied only to claims arising under a contract. However, the Disputes statute, at 41 U.S.C. 7103(g), authorizes agencies to require a contractor to continue contract performance in accordance with the contracting officer's decision pending a final resolution of any claim arising under, or relating to, the contract. (A claim arising under a contract is a claim that can be resolved under a contract clause, other than the clause at 52.233-1, Disputes, that provides for the relief sought by the claimant; however, relief for such claim can also be sought under the clause at 52.233-1. A claim relating to a contract is a claim that cannot be resolved under a contract clause other than the clause at 52.233-1.) This distinction is recognized by the clause with its *Alternate I* (see 33.215).

(b) In all contracts that include the clause at 52.233-1, Disputes, with its *Alternate I,* in the event of a dispute not arising under, but relating to, the contract, the contracting officer shall consider providing, through appropriate agency procedures, financing of the continued performance; *provided,* that the Government's interest is properly secured.

[48 FR 42349, Sept. 19, 1983. Redesignated at 50 FR 2270, Jan. 15, 1985, as amended at 64 FR 72451, Dec. 27, 1999; 67 FR 43514, June 27, 2002; 79 FR 24212, Apr. 29, 2014]