48 CFR § 4.804-4 - 4.804-4 Physically completed contracts.
---
identifier: "/us/cfr/t48/s4.804-4"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "48 CFR § 4.804-4 - 4.804-4 Physically completed contracts."
title_number: 48
title_name: "Federal Acquisition Regulations System"
section_number: "4.804-4"
section_name: "4.804-4 Physically completed contracts."
chapter_number: 1
chapter_name: "FEDERAL ACQUISITION REGULATION"
subchapter_number: "A"
subchapter_name: "GENERAL"
part_number: "4"
part_name: "ADMINISTRATIVE AND INFORMATION MATTERS"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "41 U.S.C. 1121(b); 40 U.S.C. 121(c); 10 U.S.C. chapter 4 and 10 U.S.C. chapter 137 legacy provisions (see 10 U.S.C. 3016); and 51 U.S.C. 20113."
regulatory_source: "48 FR 42113, Sept. 19, 1983, unless otherwise noted."
cfr_part: "4"
---
# 4.804-4 4.804-4 Physically completed contracts.
(a) Except as provided in paragraph (b) of this section, a contract is considered to be physically completed when—
(1)(i) The contractor has completed the required deliveries and the Government has inspected and accepted the supplies;
(ii) The contractor has performed all services and the Government has accepted these services; and
(iii) All option provisions, if any, have expired; or
(2) The Government has given the contractor a notice of complete contract termination.
(b) Rental, use, and storage agreements are considered to be physically completed when—
(1) The Government has given the contractor a notice of complete contract termination; or
(2) The contract period has expired.
[48 FR 42113, Sept. 19, 1983, as amended at 72 FR 27383, May 15, 2007; 84 FR 19841, May 6, 2019]