48 CFR § 42.1107 - 42.1107 Contract clause.
---
identifier: "/us/cfr/t48/s42.1107"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "48 CFR § 42.1107 - 42.1107 Contract clause."
title_number: 48
title_name: "Federal Acquisition Regulations System"
section_number: "42.1107"
section_name: "42.1107 Contract clause."
chapter_number: 1
chapter_name: "FEDERAL ACQUISITION REGULATION"
subchapter_number: "G"
subchapter_name: "CONTRACT MANAGEMENT"
part_number: "42"
part_name: "CONTRACT ADMINISTRATION AND AUDIT SERVICES"
positive_law: false
currency: "2026-04-05"
last_updated: "2026-04-05"
format_version: "1.1.0"
generator: "[email protected]"
authority: "41 U.S.C. 1121(b); 40 U.S.C. 121(c); 10 U.S.C. chapter 4 and 10 U.S.C. chapter 137 legacy provisions (see 10 U.S.C. 3016); and 51 U.S.C. 20113."
regulatory_source: "48 FR 42370, Sept. 19, 1983, unless otherwise noted."
cfr_part: "42"
---
# 42.1107 42.1107 Contract clause.
(a) The contracting officer shall insert the clause at 52.242-2, Production Progress Reports, in solicitations and contracts when production progress reporting is required; unless a construction contract, or a Federal Supply Schedule contract is contemplated.
(b) When the clause at 52.242-2 is used, the contracting officer shall specify appropriate reporting instructions in the Schedule (see 42.1106(a)).
[48 FR 42370, Sept. 19, 1983, as amended at 72 FR 27385, May 15, 2007]