Skip to content
LexBuild

48 CFR § 42.1301 - 42.1301 General.

---
identifier: "/us/cfr/t48/s42.1301"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "48 CFR § 42.1301 - 42.1301   General."
title_number: 48
title_name: "Federal Acquisition Regulations System"
section_number: "42.1301"
section_name: "42.1301   General."
chapter_number: 1
chapter_name: "FEDERAL ACQUISITION REGULATION"
subchapter_number: "G"
subchapter_name: "CONTRACT MANAGEMENT"
part_number: "42"
part_name: "CONTRACT ADMINISTRATION AND AUDIT SERVICES"
positive_law: false
currency: "2026-04-05"
last_updated: "2026-04-05"
format_version: "1.1.0"
generator: "[email protected]"
authority: "41 U.S.C. 1121(b); 40 U.S.C. 121(c); 10 U.S.C. chapter 4 and 10 U.S.C. chapter 137 legacy provisions (see 10 U.S.C. 3016); and 51 U.S.C. 20113."
regulatory_source: "48 FR 42370, Sept. 19, 1983, unless otherwise noted."
cfr_part: "42"
---

# 42.1301 42.1301   General.

Situations may occur during contract performance that cause the Government to order a suspension of work, or a work stoppage. This subpart provides clauses to meet these situations and a clause for settling contractor claims for unordered Government caused delays that are not otherwise covered in the contract.