48 CFR § 9.106-2 - 9.106-2 Requests for preaward surveys.
---
identifier: "/us/cfr/t48/s9.106-2"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "48 CFR § 9.106-2 - 9.106-2 Requests for preaward surveys."
title_number: 48
title_name: "Federal Acquisition Regulations System"
section_number: "9.106-2"
section_name: "9.106-2 Requests for preaward surveys."
chapter_number: 1
chapter_name: "FEDERAL ACQUISITION REGULATION"
subchapter_number: "B"
subchapter_name: "ACQUISITION PLANNING"
part_number: "9"
part_name: "CONTRACTOR QUALIFICATIONS"
positive_law: false
currency: "2026-04-05"
last_updated: "2026-04-05"
format_version: "1.1.0"
generator: "[email protected]"
authority: "41 U.S.C. 1121(b); 40 U.S.C. 121(c); 10 U.S.C. chapter 4 and 10 U.S.C. chapter 137 legacy provisions (see 10 U.S.C. 3016); and 51 U.S.C. 20113."
regulatory_source: "48 FR 42142, Sept. 19, 1983, unless otherwise noted."
cfr_part: "9"
---
# 9.106-2 9.106-2 Requests for preaward surveys.
The contracting officer's request to the surveying activity (Preaward Survey of Prospective Contractor (General), SF 1403) shall—
(a) Identify additional factors about which information is needed;
(b) Include the complete solicitation package (unless it has previously been furnished), and any information indicating prior unsatisfactory performance by the prospective contractor;
(c) State whether the contracting office will participate in the survey;
(d) Specify the date by which the report is required. This date should be consistent with the scope of the survey requested and normally shall allow at least 7 working days to conduct the survey; and
(e) When appropriate, limit the scope of the survey.