48 CFR § 1850.103-670 - 1850.103-670 Implementation of the Contract Adjustment Board's decision.
---
identifier: "/us/cfr/t48/s1850.103-670"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "48 CFR § 1850.103-670 - 1850.103-670 Implementation of the Contract Adjustment Board's decision."
title_number: 48
title_name: "Federal Acquisition Regulations System"
section_number: "1850.103-670"
section_name: "1850.103-670 Implementation of the Contract Adjustment Board's decision."
chapter_number: 18
chapter_name: "NATIONAL AERONAUTICS AND SPACE ADMINISTRATION"
subchapter_number: "G"
subchapter_name: "CONTRACT MANAGEMENT"
part_number: "1850"
part_name: "EXTRAORDINARY CONTRACTUAL ACTIONS AND THE SAFETY ACT"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "51 U.S.C. 20113(a) and 48 CFR chapter 1."
regulatory_source: "76 FR 72328, Nov. 23, 2011, unless otherwise noted."
cfr_part: "1850"
---
# 1850.103-670 1850.103-670 Implementation of the Contract Adjustment Board's decision.
(a) The contracting officer shall take action authorized in the CAB's decision.
(b) Immediately upon execution, including any required Headquarters approval, of a contract or contract modification or amendment implementing the CAB decision, the contracting officer shall forward a copy of the contractual document to the Associate General Counsel for Contracts and Procurement Law.
[76 FR 72328, Nov. 23, 2011, as amended at 80 FR 36722, June 26, 2015]