# 216.504 216.504 Indefinite-quantity contracts.
(c) *Multiple award preference*—(1) *Planning the acquisition.* (ii)(D)(*1*) The senior procurement executive has the authority to make the determination authorized in FAR 16.504(c)(1)(ii)(D)(*1*).
(*i*) In accordance with 10 U.S.C. 3403(d)(3), when making the determination at FAR 16.504(c)(1)(ii)(D)(*1*)(*i*), the senior procurement executive shall determine that the task or delivery orders expected under the contract are so integrally related that only a single source can “efficiently perform the work,” instead of “reasonably perform the work” as required by the FAR.
(*2*) The congressional notification requirement at FAR 16.504(c)(1)(ii)(D)(*2*) does not apply to DoD.
(*3*)(*i*) In accordance with 10 U.S.C. 3403(d)(3), the determination at FAR 16.504(c)(1)(ii)(D) is not required if a justification has been executed, in accordance with FAR subpart 6.3 and subpart 206.3.
[84 FR 12139, Apr. 1, 2019, as amended at 85 FR 60922, Sept. 29, 2020; 87 FR 76992, Dec. 16, 2022]