Skip to content
LexBuild

48 CFR § 217.7404 - 217.7404 Limitations.

---
identifier: "/us/cfr/t48/s217.7404"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "48 CFR § 217.7404 - 217.7404   Limitations."
title_number: 48
title_name: "Federal Acquisition Regulations System"
section_number: "217.7404"
section_name: "217.7404   Limitations."
chapter_number: 2
chapter_name: "DEFENSE ACQUISITION REGULATIONS SYSTEM, DEPARTMENT OF DEFENSE"
subchapter_number: "C"
subchapter_name: "CONTRACTING METHODS AND CONTRACT TYPES"
part_number: "217"
part_name: "SPECIAL CONTRACTING METHODS"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "41 U.S.C. 1303 and 48 CFR chapter 1."
regulatory_source: "56 FR 36345, July 31, 1991, unless otherwise noted."
cfr_part: "217"
---

# 217.7404 217.7404   Limitations.

See PGI 217.7404 for additional guidance on obtaining approval to authorize use of an undefinitized contact action, documentation requirements, and other limitations on their use.

(a) *Foreign military sales contracts.*

(1) A contracting officer may not enter into a UCA for a foreign military sale unless—

(i) The UCA provides for agreement upon contractual terms, specifications, and price by the end of the 180-day period beginning on the date on which the contractor submits a qualifying proposal; and

(ii) The contracting officer obtains approval from the head of the contracting activity to enter into a UCA in accordance with 217.7404-1.

(2) The head of the contracting activity may waive the requirements of paragraph (a)(1) of this section, if a waiver is necessary in order to support any of the following operations:

(i) A contingency operation.

(ii) A humanitarian or peacekeeping operation.

(b) *Unilateral definitization by a contracting officer.* Any UCA with a value greater than $50 million may not be unilaterally definitized until—

(1) The earlier of—

(i) The end of the 180-day period, beginning on the date on which the contractor submits a qualifying proposal to definitize the contractual terms, specifications, and price; or

(ii) The date on which the amount of funds expended under the contractual action is equal to more than 50 percent of the negotiated overall not-to-exceed price for the contractual action;

(2) The head of the contracting activity, without power of redelegation, approves the definitization in writing;

(3) The contracting officer provides a copy of the written approval to the contractor; and

(4) A period of 30 calendar days has elapsed after the written approval is provided to the contractor.