48 CFR § 237.7502 - 237.7502 Policy.
---
identifier: "/us/cfr/t48/s237.7502"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "48 CFR § 237.7502 - 237.7502 Policy."
title_number: 48
title_name: "Federal Acquisition Regulations System"
section_number: "237.7502"
section_name: "237.7502 Policy."
chapter_number: 2
chapter_name: "DEFENSE ACQUISITION REGULATIONS SYSTEM, DEPARTMENT OF DEFENSE"
subchapter_number: "F"
subchapter_name: "SPECIAL CATEGORIES OF CONTRACTING"
part_number: "237"
part_name: "SERVICE CONTRACTING"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "41 U.S.C. 1303 and 48 CFR chapter 1."
regulatory_source: "56 FR 36424, July 31, 1991, unless otherwise noted."
cfr_part: "237"
---
# 237.7502 237.7502 Policy.
(a) Comply with DoD Directive 4275.5, Acquisition and Management of Industrial Resources, in processing requests for facilities projects.
(b) Departments and agencies shall submit reports of facilities projects to the House and Senate Armed Services Committees—
(1) At least 30 days before starting facilities projects involving real property (10 U.S.C. 2662); and
(2) In advance of starting construction for a facilities project regardless of cost. Use DD Form 1391, FY____ Military Construction Project Data, to notify congressional committees of projects that are not included in the annual budget.