48 CFR § 242.1107 - 242.1107 Contract clause.
---
identifier: "/us/cfr/t48/s242.1107"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "48 CFR § 242.1107 - 242.1107 Contract clause."
title_number: 48
title_name: "Federal Acquisition Regulations System"
section_number: "242.1107"
section_name: "242.1107 Contract clause."
chapter_number: 2
chapter_name: "DEFENSE ACQUISITION REGULATIONS SYSTEM, DEPARTMENT OF DEFENSE"
subchapter_number: "G"
subchapter_name: "CONTRACT MANAGEMENT"
part_number: "242"
part_name: "CONTRACT ADMINISTRATION AND AUDIT SERVICES"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "41 U.S.C. 1303 and 48 CFR chapter 1."
regulatory_source: "56 FR 36437, July 31, 1991, unless otherwise noted."
cfr_part: "242"
---
# 242.1107 242.1107 Contract clause.
(b) When using the clause at FAR 52.242-2, include the following instructions in the contract schedule—
(i) Frequency and timing of reporting (normally 5 working days after each reporting period);
(ii) Contract line items, exhibits, or exhibit line items requiring reports;
(iii) Offices (with addressees/codes) where reports should be sent (always include the contracting office and contract administration office); and
(iv) The following requirements for report content—
(A) The problem, actual or potential, and its cause;
(B) Items and quantities affected;
(C) When the delinquency started or will start;
(D) Actions taken to overcome the delinquency;
(E) Estimated recovery date; and/or
(F) Proposed schedule revision.