Skip to content
LexBuild

48 CFR § 552.246-72 - 552.246-72 Final Inspection and Tests.

---
identifier: "/us/cfr/t48/s552.246-72"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "48 CFR § 552.246-72 - 552.246-72   Final Inspection and Tests."
title_number: 48
title_name: "Federal Acquisition Regulations System"
section_number: "552.246-72"
section_name: "552.246-72   Final Inspection and Tests."
chapter_number: 5
chapter_name: "GENERAL SERVICES ADMINISTRATION"
subchapter_number: "H"
subchapter_name: "CLAUSES AND FORMS"
part_number: "552"
part_name: "SOLICITATION PROVISIONS AND CONTRACT CLAUSES"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "40 U.S.C. 121(c)."
regulatory_source: "64 FR 37229, July 9, 1999, unless otherwise noted."
cfr_part: "552"
---

# 552.246-72 552.246-72   Final Inspection and Tests.

As prescribed in 546.312, insert the following clause:

****Final Inspection and Tests (SEP 1999)

The Contractor shall give written notice to the Contracting Officer at least 10 calendar days before the date the work will be completed and ready for final inspection and tests. Final inspection and tests will begin within 10 calendar days after the date specified in the Contractor's notice unless the Contracting Officer determines that the work is not ready for final inspection and so informs the Contractor.

****(End of clause)