Skip to content
LexBuild

48 CFR § 817.7004-3 - 817.7004-3 Definitization schedule.

---
identifier: "/us/cfr/t48/s817.7004-3"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "48 CFR § 817.7004-3 - 817.7004-3   Definitization schedule."
title_number: 48
title_name: "Federal Acquisition Regulations System"
section_number: "817.7004-3"
section_name: "817.7004-3   Definitization schedule."
chapter_number: 8
chapter_name: "DEPARTMENT OF VETERANS AFFAIRS"
subchapter_number: "C"
subchapter_name: "CONTRACTING METHODS AND CONTRACT TYPES"
part_number: "817"
part_name: "SPECIAL CONTRACTING METHODS"
positive_law: false
currency: "2026-04-05"
last_updated: "2026-04-05"
format_version: "1.1.0"
generator: "[email protected]"
authority: "38 U.S.C. 8127-8128; 41 U.S.C. 1303; 41 U.S.C. 1702; and 48 CFR 1.301-1.304."
regulatory_source: "73 FR 2717, Jan. 15, 2008, unless otherwise noted."
cfr_part: "817"
---

# 817.7004-3 817.7004-3   Definitization schedule.

(a) UCAs shall contain definitization schedules that provide for definitization by the earlier of—

(1) The date that is 180 days after issuance of the action (this date may be extended but may not exceed the date that is 180 days after the contractor submits a definitization proposal); or

(2) The date on which the amount of funds paid to the contractor under the contract action is equal to more than 50 percent of the not-to-exceed price.

(b) Submission of a definitization proposal in accordance with the definitization schedule is a material element of the contract. If the contractor does not submit a timely definitization proposal, the contracting officer may suspend or reduce progress payments under FAR 32.503-6, or take other appropriate action.