Skip to content
LexBuild

48 CFR § 817.7004-4 - 817.7004-4 Final price negotiation—profit.

---
identifier: "/us/cfr/t48/s817.7004-4"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "48 CFR § 817.7004-4 - 817.7004-4   Final price negotiation—profit."
title_number: 48
title_name: "Federal Acquisition Regulations System"
section_number: "817.7004-4"
section_name: "817.7004-4   Final price negotiation—profit."
chapter_number: 8
chapter_name: "DEPARTMENT OF VETERANS AFFAIRS"
subchapter_number: "C"
subchapter_name: "CONTRACTING METHODS AND CONTRACT TYPES"
part_number: "817"
part_name: "SPECIAL CONTRACTING METHODS"
positive_law: false
currency: "2026-04-05"
last_updated: "2026-04-05"
format_version: "1.1.0"
generator: "[email protected]"
authority: "38 U.S.C. 8127-8128; 41 U.S.C. 1303; 41 U.S.C. 1702; and 48 CFR 1.301-1.304."
regulatory_source: "73 FR 2717, Jan. 15, 2008, unless otherwise noted."
cfr_part: "817"
---

# 817.7004-4 817.7004-4   Final price negotiation—profit.

Before the final price of a UCA is negotiated, contracting officers shall ensure the profit agreed to and documented in the contract negotiation memorandum reflects consideration of any risks incurred in performance of the work under the UCA.