Skip to content
LexBuild

49 CFR § 192.719 - Transmission lines: Testing of repairs.

---
identifier: "/us/cfr/t49/s192.719"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "49 CFR § 192.719 - Transmission lines: Testing of repairs."
title_number: 49
title_name: "Transportation"
section_number: "192.719"
section_name: "Transmission lines: Testing of repairs."
chapter_name: "PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION, DEPARTMENT OF TRANSPORTATION"
subchapter_number: "D"
subchapter_name: "PIPELINE SAFETY"
part_number: "192"
part_name: "TRANSPORTATION OF NATURAL AND OTHER GAS BY PIPELINE: MINIMUM FEDERAL SAFETY STANDARDS"
positive_law: false
currency: "2026-04-05"
last_updated: "2026-04-05"
format_version: "1.1.0"
generator: "[email protected]"
authority: "30 U.S.C. 185(w)(3), 49 U.S.C. 5103, 60101  and 49 CFR 1.97."
regulatory_source: "35 FR 13257, Aug. 19, 1970, unless otherwise noted."
cfr_part: "192"
---

# 192.719 Transmission lines: Testing of repairs.

(a) *Testing of replacement pipe.* If a segment of transmission line is repaired by cutting out the damaged portion of the pipe as a cylinder, the replacement pipe must be tested to the pressure required for a new line installed in the same location. This test may be made on the pipe before it is installed.

(b) *Testing of repairs made by welding.* Each repair made by welding in accordance with §§ 192.713, 192.715, and 192.717 must be examined in accordance with § 192.241.

[35 FR 13257, Aug. 19, 1970, as amended by Amdt. 192-54, 51 FR 41635, Nov. 18, 1986]