Skip to content
LexBuild

49 CFR § 633.23 - FTA review of a project management plan.

---
identifier: "/us/cfr/t49/s633.23"
source: "ecfr"
legal_status: "authoritative_unofficial"
title: "49 CFR § 633.23 - FTA review of a project management plan."
title_number: 49
title_name: "Transportation"
section_number: "633.23"
section_name: "FTA review of a project management plan."
chapter_name: "FEDERAL TRANSIT ADMINISTRATION, DEPARTMENT OF TRANSPORTATION"
part_number: "633"
part_name: "PROJECT MANAGEMENT OVERSIGHT"
positive_law: false
currency: "2026-03-24"
last_updated: "2026-03-24"
format_version: "1.1.0"
generator: "[email protected]"
authority: "49 U.S.C. 5327; 49 U.S.C. 5334; 49 CFR 1.90."
regulatory_source: "85 FR 59679, Sept. 23, 2020, unless otherwise noted."
cfr_part: "633"
---

# 633.23 FTA review of a project management plan.

Within 60 days of receipt of a project management plan, the Administrator will notify the recipient that:

(a) The plan is approved;

(b) The plan is disapproved, including the reasons for the disapproval;

(c) The plan will require modification, as specified, before approval; or

(d) The Administrator has not yet completed review of the plan, and state when it will be reviewed.