# 18.107 Mitigation.
(a) *Mitigation measures for all LOAs.* The applicant, including all personnel operating under the applicant's authority (or “operators,” including contractors, subcontractors, and representatives) must undertake the following activities to avoid and minimize take of sea otters by harassment.
(1) Implement policies and procedures to avoid interactions with and minimize to the greatest extent practicable adverse impacts on sea otters, their habitat, and the availability of these marine mammals for subsistence uses.
(2) Develop avoidance and minimization policies and procedures, in cooperation with the FWS, that include temporal or spatial activity restrictions to be used in response to the presence of sea otters engaged in a biologically significant activity (*e.g.,* resting, feeding, hauling out, mating, or nursing).
(3) Cooperate with the FWS's MMM Office and other designated Federal, State, and local agencies to monitor and mitigate the impacts of pile driving and marine construction activities on sea otters.
(4) Allow FWS personnel or the FWS's designated representative to board project vessels or visit project worksites for the purpose of monitoring impacts to sea otters and to subsistence uses of sea otters at any time throughout project activities so long as it is safe to do so.
(5) Designate trained and qualified protected species observers (PSOs) to monitor for the presence of sea otters, initiate mitigation measures, and monitor, record, and report the effects of the activities on sea otters. The applicant is responsible for providing training to PSOs to carry out mitigation and monitoring.
(6) Have an approved mitigation and monitoring plan on file with the FWS MMM and onsite that includes the following information:
(i) The type of activity and where and when the activity will occur (*i.e.,* a summary of the plan of operation);
(ii) Personnel training policies, procedures, and materials;
(iii) Site-specific sea otter interaction risk evaluation and mitigation measures;
(iv) Sea otter avoidance and encounter procedures; and
(v) Sea otter observation and reporting procedures.
(b) *Mitigation measures for in-water noise-generating work.* The applicant must carry out the following measures:
(1) Construction activities must be conducted using equipment that generates the lowest practicable levels of in-water noise within the range of frequencies audible to sea otters.
(2) If a sea otter enters or appears likely to enter the shutdown zone, in-water activities must be shut down until either the sea otter has been visually observed outside the shutdown zone or at least 15 minutes have elapsed since the last observation time without redetection of the sea otter.
(i) During in-water activities at Seward, an acoustic shutdown zone of 85 meters (m; 280 feet [ft]) must be enforced during down-the-hole (DTH) drilling of concrete piles, and a shutdown zone of 30 m (99 ft) must be enforced during all other in-water activities.
(ii) During in-water activities at Sitka and Kodiak, regardless of predicted sound levels, a physical interaction shutdown zone of at least 20 m (66 ft) must be enforced.
(3) If the impact driver has been idled for more than 30 minutes, an initial set of three strikes from the impact driver must be delivered (at reduced energy if possible), followed by a 1-minute waiting period. This procedure will be conducted a total of three times before full-powered strikes if practicable. If unsafe working conditions during soft-starts occur (*e.g.,* equipment failure), then the applicant may elect to discontinue soft-starts, and the applicant must notify the FWS if the soft-start procedure is discontinued.
(4) If practicable, a soft-start procedure for vibratory pile-driving activities may be implemented if the vibratory hammer has been idled for more than 30 minutes. During the soft-start procedure, initial noise generation must be limited to 15 seconds (at reduced energy if possible), followed by a 1-minute waiting period. This procedure will be conducted a total of three times before full-powered vibratory pile driving commences. If unsafe working conditions during soft-starts occur (*e.g.,* equipment failure), then the applicant may elect to discontinue soft-starts and the applicant must notify the FWS if the soft-start procedure is discontinued.
(5) In-water activity must be conducted in daylight. If environmental conditions prevent visual detection of sea otters within the shutdown zone, in-water activities must be stopped until visibility is regained.
(6) All in-water work along the shoreline must be conducted during lower tidal conditions when the site is dewatered to the maximum extent practicable.
(7) When practicable, or when required by applicable local, State, or Federal regulations, the applicant must use containment methods (*e.g.,* silt curtains) to isolate areas with high levels of turbidity during DTH drilling and vibroflot column installation.
(c) *Mitigation measures for vessel operations.* Vessel operators must take every precaution to avoid harassment of sea otters during vessel operations. The applicant must carry out the following measures:
(1) Vessels must maintain a minimum distance of 500 m (0.3 mile [mi]) from rafts of 10 or more sea otters unless otherwise needed for safety. If a vessel must transit within 500 m (0.3 mi) from rafts of sea otters, the vessel must travel at a reduced speed and maintain the maximum distance practicable between the vessel and raft of sea otters. Vessels must reduce speed and maintain a minimum distance of 100 m (328 ft) from all sea otters unless otherwise needed for safety.
(2) Vessels must not be operated in such a way as to separate members of a group of sea otters (two or more sea otters) from other members of the group, encircle sea otters, or impede movement of sea otters. Vessels must use established navigation channels or commonly recognized vessel traffic corridors and avoid approaching sea otters or impeding sea otter movements when traveling near the shoreline in shallow water (<20 m [<66 ft]) whenever practicable.
(3) When weather conditions require, such as when visibility drops, vessels must adjust speed accordingly to reduce the likelihood of injury to sea otters.
(4) Vessel operators must be provided written guidance for avoiding collisions and minimizing disturbances to sea otters. Guidance will include measures identified in paragraphs (c)(1) through (4) of this section.
(d) *Mitigation measures for the subsistence use of sea otters.* Holders of an LOA must conduct their activities in a manner that, to the greatest extent practicable, minimizes adverse impacts on the availability of sea otters for subsistence uses.
(1) *Community consultation.* Prior to receipt of an LOA, applicants must consult with potentially affected communities and appropriate subsistence user organizations to discuss potential conflicts with subsistence sea otter hunting caused by the location, timing, and methods of operations and support activities (see § 18.103 for details). If community concerns suggest that the activities may have an adverse impact on the subsistence uses of this species, the applicant must address conflict avoidance issues through a POC as described in paragraph (d)(2) of this section.
(2) *Plan of cooperation.* Based on community consultations, the holder of an LOA will be required to modify their POC if directed by the FWS.
(i) The POC must include a description of the procedures by which the holder of the LOA will work and consult with potentially affected subsistence hunters and a description of specific measures that have been or will be taken to avoid or minimize interference with subsistence hunting of sea otters and to ensure continued availability of the species for subsistence use.
(ii) The FWS will review the POC to ensure that any potential adverse effects on the availability of sea otters are minimized. The FWS will reject POCs if they do not provide adequate safeguards to ensure the least practicable adverse impact on the availability of sea otters for subsistence use.