Rates for Pilotage on the Great Lakes

---
identifier: "/us/fr/04-226"
source: "fr"
legal_status: "authoritative_unofficial"
title: "Rates for Pilotage on the Great Lakes"
title_number: 0
title_name: "Federal Register"
section_number: "04-226"
section_name: "Rates for Pilotage on the Great Lakes"
positive_law: false
currency: "2004-01-06"
last_updated: "2004-01-06"
format_version: "1.1.0"
generator: "[email protected]"
agency: "Homeland Security Department"
document_number: "04-226"
document_type: "rule"
publication_date: "2004-01-06"
agencies:
  - "Homeland Security Department"
  - "Coast Guard"
cfr_references:
  - "46 CFR Part 401"
  - "46 CFR Part 404"
rin: "2115-AG30"
fr_citation: "69 FR 533"
fr_volume: 69
docket_ids:
  - "USCG-2002-11288"
effective_date: "2004-01-06"
fr_action: "Correction to interim rule."
---

#  Rates for Pilotage on the Great Lakes

**AGENCY:**

Coast Guard, DHS.

**ACTION:**

Correction to interim rule.

**SUMMARY:**

This document contains corrections to the interim rule [USCG-2002-11288], which was published in the *Federal Register* on December 12, 2003 (68 FR 69564). The interim rule provides a partial rate adjustment for pilotage on the Great Lakes. A review of this interim rule after publication identified an omission of a figure in a table and two erroneous tables.

**DATES:**

Effective on January 6, 2004.

**FOR FURTHER INFORMATION CONTACT:**

For questions on this correction notice, call or e-mail Paul Wasserman, Director, Office of Great Lakes Pilotage (G-MW-1), U.S. Coast Guard, at telephone 202-267-2856, or *[email protected].*

**SUPPLEMENTARY INFORMATION:**

**Need for Correction**

The interim rule, as published, contained an erroneous figure for the total of District One's Projected Return on Investment. This was due to the omission of a number in the column designated as “Total District One.” There were also two incorrect tables placed in Step 6a. The tables should have been “Table B.—District Two—Projected Return on Investment” and Table C.—District Three—Projected Return on Investment.”

**Correction of Publication**

Accordingly, the publication on December 12, 2003, of the interim rule [USCG-2002-11288], FR Doc. 03-30711, is corrected as follows:

1. On page 69574, in Table A.—District One Step 10, change the figure under Total District One from $10,000 to $100,000.

2. On page 69574, remove “Table B.—District Two—Adjustment Determination” and “Table C.—District Three—Adjustment Determination” and, in their place, add the following tables.

| Step | Area 4 | Area 5 | Total District 2 |
| --- | --- | --- | --- |
| 1 | $705,015 | $1,461,069 | $2,166,084 |
| 2 | (365,292) | (446,468) | (811,760) |
| 3 | (477,218) | (930,701) | (1,407,919) |
| 4 | (137,495) | 83,900 | (53,595) |
| 5 | 0 | 0 | 0 |
| 6 | (137,495) | 83,900 | (53,595) |
| 7 | 0 | 0 | 0 |
| 8 | (137,495) | 83,900 | (53,595) |
| 9 | (137,495) | 83,900 | (53,595) |
| 10 | 89,734 | 140,353 | 230,087 |
| 11 | (1.593) | 0.559 | (0.280) |

| Step | Area 6 | Area 7 | Area 8 | Total District 1 |
| --- | --- | --- | --- | --- |
| 1 | $1,540,306 | $1,119,819 | $1,030,693 | $3,690,818 |
| 2 | (739,550) | (292,739) | (508,441) | (1,540,730) |
| 3 | (1,099,676) | (625,315) | (715,827) | (2,440,818) |
| 4 | (298,920) | 201,765 | (193,575) | (290,730) |
| 5 | 0 | 0 | 0 | 0 |
| 6 | (298,920) | 201,765 | (193,575) | (290,730) |
| 7 | 0 | 0 | 0 | 0 |
| 8 | (298,920) | 201,765 | (193,575) | (290,730) |
| 9 | (298,920) | 201,765 | (193,575) | (290,730) |
| 10 | 111,668 | 83,752 | 83,752 | 279,172 |
| 11 | (2.677) | 2.409 | (2.311) | (1.041) |

Dated: December 30, 2003.

Joseph J. Angelo,