Connecticut Transmission Infrastructure; New England Power Pool and ISO New England, Inc., et al.; Devon Power LLC, et al.; Exelon New Boston LLC; ISO New England, Inc.; ISO New England, Inc. and Bangor Hydro, et al.; Notice of Technical Conference

---
identifier: "/us/fr/E5-45"
source: "fr"
legal_status: "authoritative_unofficial"
title: "Connecticut Transmission Infrastructure; New England Power Pool and ISO New England, Inc., et al.; Devon Power LLC, et al.; Exelon New Boston LLC; ISO New England, Inc.; ISO New England, Inc. and Bangor Hydro, et al.; Notice of Technical Conference"
title_number: 0
title_name: "Federal Register"
section_number: "E5-45"
section_name: "Connecticut Transmission Infrastructure; New England Power Pool and ISO New England, Inc., et al.; Devon Power LLC, et al.; Exelon New Boston LLC; ISO New England, Inc.; ISO New England, Inc. and Bangor Hydro, et al.; Notice of Technical Conference"
positive_law: false
currency: "2005-01-11"
last_updated: "2005-01-11"
format_version: "1.1.0"
generator: "[email protected]"
agency: "Energy Department"
document_number: "E5-45"
document_type: "notice"
publication_date: "2005-01-11"
agencies:
  - "Energy Department"
  - "Federal Energy Regulatory Commission"
fr_citation: "70 FR 1887"
fr_volume: 70
docket_ids:
  - "Docket Nos. PL04-14-000, ER03-1141-004, EL03-222-004, EL04-102-004, EL04-102-005, EL04-102-007, EL04-102-008, ER03-563-025, ER03-563-027, ER03-563-033, ER03-563-036, ER03-563-043, ER03-563-044, ER03-563-045, ER03-563-047, ER03-563-048, ER04-464-002, ER04-"
---

#  Connecticut Transmission Infrastructure; New England Power Pool and ISO New England, Inc., et al.; Devon Power LLC, et al.; Exelon New Boston LLC; ISO New England, Inc.; ISO New England, Inc. and Bangor Hydro, et al.; Notice of Technical Conference

In a Notice of Technical Conference issued October 29, 2004, the Federal Energy Regulatory Commission announced that it would host a technical conference on Thursday, January 6, 2005, to discuss specific transmission proposals and cost issues for the State of Connecticut. The conference will be held in Room 2C of the Legislative Office Building, 300 Capitol Avenue, Hartford, Connecticut.

Please take note that the workshop schedule has changed, to begin at 10 a.m. (EST) (instead of 9 a.m.) and end at approximately 1 p.m. (instead of 3 p.m.). Members of the Federal Energy Regulatory Commission are expected to participate, along with state regulators from the New England region. An agenda is attached to this notice.

This conference is a follow-up to the infrastructure conference that was held on October 13, 2004. The goal of this technical conference is to provide a forum for discussion of issues affecting energy infrastructure in and around Connecticut. This discussion will take place between federal, State and regional leaders and industry representatives. The January 6 conference will focus primarily on proposals for new electric transmission, and the costs of these proposals.

The conference is a technical discussion between policy leaders, however, members of the public are welcome to attend. Registration is not required; however, in-person attendees are asked to register for the conference on-line by close of business on Tuesday,  January 4, 2005 at *http://www.ferc.gov/whats-new/registration/infra-0106-form.asp.*

Transcripts of the conference will be immediately available from Ace Reporting Company (202-347-3700 or 1-800-336-6646) for a fee. They will be available for the public on the Commission's eLibrary system seven calendar days after FERC receives the transcript. Additionally, Capitol Connection offers the opportunity for remote listening of the conference via Real Audio or a Phone Bridge Connection for a fee. Persons interested in making arrangements should contact David Reininger or Julia Morelli at the Capitol Connection (703-993-3100) as soon as possible or visit the Capitol Connection Web site at *http://www.capitolconnection.org* and click on “FERC.”

For more information about the conference, please contact Sarah McKinley at 202-502-8004, *[email protected].*

Magalie R. Salas,

Secretary.

**Addenda A**

**Agenda—Technical Conference on Connecticut Infrastructure; Thursday, January 6, 2005; Hartford, Connecticut; 10 a.m. to 1 p.m.**

**Opening Comments**

Chairman Pat Wood, III, Federal Energy Regulatory Commission.

Chairman Donald W. Downes, Connecticut Department of Public Utility Control.

**Review of Issues**

David H. Boguslawski, Vice President, Transmission Business, Northeast Utilities Service Company.

**Scope and Findings of the Investigations**

Stephen G. Whitley, Senior Vice President and Chief Operating Officer, ISO New England, Inc.

**Solutions Before the Siting Council**

John J. Prete, Project Director/General Manager and Vice President, United Illuminating.

**Cost Comparisons of Solutions**

Anne Bartosewicz, Transmission Project Director, Northeast Utilities System.

**Reliability Benefits**

Stephen G. Whitley, Senior Vice President and Chief Operating Officer, ISO New England, Inc.

**Process Going Forward for Determining Cost Allocation**

Stephen G. Whitley, Senior Vice President and Chief Operating Officer, ISO New England, Inc.

**Summary**

David H. Boguslawski, Vice President, Transmission Business, Northeast Utilities Service Company.