American Electric Power Service Corporation; PJM Interconnection, LLC and Midwest Independent Transmission System Operator, Inc.; Notice Instituting Section 206 Proceeding and Establishing Effective Refund Date
---
identifier: "/us/fr/E5-1148"
source: "fr"
legal_status: "authoritative_unofficial"
title: "American Electric Power Service Corporation; PJM Interconnection, LLC and Midwest Independent Transmission System Operator, Inc.; Notice Instituting Section 206 Proceeding and Establishing Effective Refund Date"
title_number: 0
title_name: "Federal Register"
section_number: "E5-1148"
section_name: "American Electric Power Service Corporation; PJM Interconnection, LLC and Midwest Independent Transmission System Operator, Inc.; Notice Instituting Section 206 Proceeding and Establishing Effective Refund Date"
positive_law: false
currency: "2005-03-16"
last_updated: "2005-03-16"
format_version: "1.1.0"
generator: "[email protected]"
agency: "Energy Department"
document_number: "E5-1148"
document_type: "notice"
publication_date: "2005-03-16"
agencies:
- "Energy Department"
- "Federal Energy Regulatory Commission"
fr_citation: "70 FR 12860"
fr_volume: 70
docket_ids:
- "Docket Nos. ER05-31-000, ER05-31-001, and EL05-70-000"
---
# American Electric Power Service Corporation; PJM Interconnection, LLC and Midwest Independent Transmission System Operator, Inc.; Notice Instituting Section 206 Proceeding and Establishing Effective Refund Date
On March 9, 2005, the Commission issued an order in the above-referenced dockets instituting a proceeding in Docket No. EL05-70-000 under section 206 of the Federal Power Act.
The refund effective date in Docket No. EL05-70-000, established pursuant to section 206 of the Federal Power Act, will be 60 days following publication of this notice in the *Federal Register* .
Magalie R. Salas,
Secretary.