title_name: "Federal Register"
section_number: "E5-911"
section_name: "Delmarva Power & Light Company; PJM Interconnection, LLC; Notice of Initiation of Proceeding and Refund Effective Date"
positive_law: false
currency: "2005-03-07"
last_updated: "2005-03-07"
format_version: "1.1.0"
generator: "[email protected]"
agency: "Energy Department"
document_number: "E5-911"
document_type: "notice"
publication_date: "2005-03-07"
agencies:
  - "Energy Department"
  - "Federal Energy Regulatory Commission"
fr_citation: "70 FR 11001"
fr_volume: 70
docket_ids:
  - "Docket Nos. ER04-509-000, ER04-509-001, ER04-509-002, ER04-509-003, ER04-509-004, ER04-1250-000, ER04-1250-001, ER04-1250-002, ER04-1250-003, and EL05-62-000"
---

#  Delmarva Power & Light Company; PJM Interconnection, LLC; Notice of Initiation of Proceeding and Refund Effective Date

On February 25, 2005, the Commission issued an order in the above-referenced dockets initiating a proceeding in Docket No. EL05-62-000 under section 206 of the Federal Power Act. 110 FERC ¶ 61,186 (2005).

The refund effective date in Docket No. EL05-62-000, established pursuant to section 206 of the Federal Power Act, will be 60 days following publication of this notice in the *Federal Register* .

Magalie R. Salas,

Secretary.